Last week some pre-demolition work related to utilities and clearing continued on the site. The old library was used for a "haunted house" on Friday, October 26 from 3 pm to 6 pm. SMCL opened the temporary library last week at the corner of Dinkelspiel and Maple Ave.
There currently is an on-line suction only going on to sell any equipment, artifacts, desks, etc. no longer needed by the Library and Public Works. https://online.auctionnation.com/auction/13778.
On October 30th, Staff is having the pre-construction meeting with Central Valley Environmental (CVE), the Contractor that was awarded the demolition contract by City Council to discuss working hours, parking, noise, dust control, schedule, and other project related issues. Per the contract, CVE will have thirty working days to complete all the work. All project related documents can be found at: http://www.ci.atherton.ca.us/bids.aspx?bidID=61
Once the demolition of the site begins, there will be construction fencing, trucks, dust and noise. Demolition will take place between the hours of Monday through Friday, 8 am to 5 pm.