The Town of Atherton has contracted NV5 (Nolte) for Structural Bridge/Culvert inspections along the Atherton Channel.
Weather permitting, the inspections will start on Monday, October13th and the completion date is Friday, October 24th. Work hours are between 8 AM – 5 PM. The consultant (NV5 or Nolte) and their subs (Subtronics) can be identified by their Fluorescent Green/Orange vests with their Companies name on it. Please do not be alarmed by their accessing these areas by gates and ladders.
The consultant will be inspecting structures at the following locations.
NO. - Location - Type (approx)
1 - 11 Belbrook - 60" CMP
2 - 358 Walsh - Box Culvert
3 - 24 Broad Acres - Bridge
4 - Alameda de Pulgas @ Walsh - Box
5 - 279 Camino Al Lago - Box
6 - Camino Al Lago @ Monte Vista - Box
7 - 59 Barry - Box
8 - 55 Elena - Box
9 - 100 Isabella - Box
10 - Watkins (from ECR to SPRR) - Box
11 - 150 Watkins - 2- Bridge
12 - Middlefield (from Watkins to Marsh) - Box
Inspections will begin at #12 - Middlefield Road and Marsh Road and head upstream towards #1 – Belbrook Way
If you have additional questions, please contact Public Works at 650-752-0570.