ATHERTON ROAD WORK CONTINUES
PHASE 2 of the Atherton Ave-Fair Oaks Ln.-Middlefield Rd. Maintenance Project begins June 22nd.
Phase 1 construction on Atherton Ave and Fair Oaks Lane was completed on May 4th. Pavement failures were repaired in preparation for a Type II micro surface. This micro surface will take place on the following streets: Atherton Avenue, Fair Oaks Lane and Middlefield Road.
Updated Construction schedule with detour plan see link below.
Middlefield Road will continue to have traffic in both directions. There will be no left turn pocket during these dates. Even though our best efforts will be to assure traffic delays are kept to a minimum, a plan on your part to avoid these streets during this timeframe (if possible) might save you some delays and frustration.
Pavement markings and striping will begin after the Independence Day Holiday.