To: All Residents,
Re: 2016 Spring Patching Project (Project #56070)
The Town of Atherton has contracted G. Bortolotto & Co. for the 2016 Spring Patching Project. The contractor is contracted to perform asphalt concrete pavement base failure repair (patching) in your neighborhood. Weather permitting, work will start on Tuesday, March 15th (Postponed for one day due to rain) and the anticipated completion date is Monday, April 4. Work hours are between 8AM and 5PM.
During this time, you will experience some delays including traffic and roadway detours.
Residents and household personnel will be provided access to their property at all times.
Construction start date: Tuesday, March 15th
Day #1 and #2 (3/15, 3/17)
Dig outs: Greenoaks Drive
Traffic Control Plan for Greenoaks Drive can be reviewed at the web address below:
http://ca-atherton.civicplus.com/DocumentCenter/View/2857
Day #2, #3 and #4 (3/17, 3/18, 3/21)
Dig outs: Oak Grove Avenue, Ashfield Road, Stockbridge, Euclid
Day #4 and #5 (3/21 – 3/22)
Dig outs: Alameda de Las Pulgas, Linda Vista Avenue
Day #6 and #7 (3/23 – 3/24)
Dig outs: Camino Al Lago
For additional questions and information, please contact the Public Works Department at 650-752-0570.
Sincerely,
David Huynh, PE
Associate Engineer